My neighborhood was recently involved in a class action lawsuit against the builder for construction defects. Among the myriad defects found in the house, it was discovered that the bathroom shower enclosures were not correctly waterproofed. I *finally* had that repair work done, along with some other repairs that I've been putting off forever! Now, unfortunately, I need to deal with repairs on the repair work... I am not a happy camper.
This page shows the progress from beginning to end (most recent on top). Click on the "Week of..." links to see the gory details!
| Before... | |
| ...and After | |
| Week of 6/24 | |||
| Paint and the finishing details... moments before my family arrived on June 30th. | |||
| Week of 6/17 | |||
| The new bathroom vinyl is installed... and I unhappily discover that the new shower enclosure needs at least two more coats of grout sealer. | |||
| Week of 6/03 | |||
| New kitchen faucet; vinyl decisions. | |||
| Week of 5/27 | |||
| Sean takes the week off, and I start decorating. | |||
| Week of 5/20 | |||
| The guest bath is *almost* done! Yay! | |||
|
Tile and grout are done |
Backsplash is almost done |
New light fixture in the front yard |
|
|
Week of 5/13 |
|||
| Things heat up... but an honest discussion leads to an amicable solution. | |||
|
The tile is almost done. |
Sean installs the second light fixture and adjusts the first one. |
||
|
Week of 5/6 |
|||
| The beat goes on.... er, at least the tiling does. | |||
|
The tile is about half way done. |
Backsplash demolition begins. |
||
|
Week of 4/29 |
|||
| This week the tiling begins... but we've still got a long way to go! | |||
|
The tiling begins... |
Here's the tile and the decorative accent. |
||
|
Week of 4/22 |
|||
| This week... the reconstruction begins. Installation begins on faucets and light fixtures. We're side-tracked by the need to replace the water shutoff valve on the side of the house, but by weeks end, final decisions have been made on the lights, faucets and tile... and Sean and I are starting to figure each other out. | |||
|
One light... |
one faucet... |
and a brand new water valve. |
|
|
Week of 4/15 |
|||
|
Well, the terror, er work, has begun. Poor Sean. I'm so intimidated by
everything. Everytime he tries to explain all the work that needs to be done,
all I see are the dollar signs. Sean favorite word this week: RELAX! By the end of the first week, the demolition is done in the guest bath. Next week, we start putting it all back together. Big decisions must be made regarding tile and faucets. |
|||
|
Whole house fan installation |
Demolition begins |
||